> Class A fit-out budgets in 2026 sit at USD 200–400/sf in US gateway cities for institutional standard.

## TL;DR

- Class A fit-out budgets in 2026 sit at USD 200–400/sf in US gateway cities for institutional standard.
- Trophy fit-outs (executive floors, client-facing, full amenity) reach USD 500–800/sf.
- Schedules: 18–28 weeks design + permit, 16–28 weeks construction.
- Permitting is the single biggest schedule risk in NYC, SF, LA.
- Material lead times for AV, custom millwork, and specialty MEP remain extended.

# Fit-out construction in 2026: budget, schedule, risk

By The [Class A](/glossary/class-a) Atlas Editorial Desk · 2025-10-01T00:00:00.000Z · 10 min read

**An updated working view of Class A [fit-out](/topics/fit-out-capex)">fit-out construction economics, schedules, and risk allocation.**

## TL;DR

- Class A fit-out budgets in 2026 sit at USD 200–400/sf in US gateway cities for institutional standard.
- Trophy fit-outs (executive floors, client-facing, full amenity) reach USD 500–800/sf.
- Schedules: 18–28 weeks design + permit, 16–28 weeks construction.
- Permitting is the single biggest schedule risk in NYC, SF, LA.
- Material lead times for AV, custom millwork, and specialty MEP remain extended.

## Budget bands

Class A institutional fit-out budgets in 2026 run USD 200–400/sf in US gateway cities (NYC, SF, Chicago, LA, DC, Boston). Trophy fit-outs with executive floors, full-amenity client-facing functions, and bespoke millwork reach USD 500–800/sf. London equivalents convert at GBP 180–350/sf institutional, GBP 400–650/sf trophy.

## Schedule structure

Standard schedule: 4–6 weeks design programming, 8–14 weeks design development to issued-for-permit, 6–12 weeks permitting, 16–28 weeks construction. Total: 34–60 weeks from kickoff to occupancy. Compress where possible by using design-build contractors and pre-permitted spec suites.

## Permitting risk

Permitting is the single biggest schedule risk. NYC DOB, SF DBI, and LA LADBS routinely run 6–12 weeks for office fit-out permits and longer if structural, fire-life-safety, or change-of-use is involved. Build the float into the LOI, not the move-in date.

## Material lead times

Specialty AV (control rooms, broadcast, large-format displays), custom millwork, specialty MEP (UPS, in-floor power, secure rooms), and high-end glazing all run 16–32 week lead times in 2026. Order at design-development sign-off, not construction kickoff.

## Risk allocation

Best-practice contracting: GMP construction with shared savings, owner contingency 5–8%, owner-controlled allowances on long-lead AV/IT, third-party commissioning, and a project-management firm separate from the architect. Don't let any single party own all four roles.

## Frequently asked questions

****Is the TI allowance enough to cover the build?****
: Rarely for a trophy fit-out. Plan for USD 50–150/sf of overrun above TI on a trophy build. Negotiate amortisation of the overrun into rent at a reasonable cost of capital.

****Should I use the landlord's preferred contractor?****
: Sometimes — they may know the building, but typically they negotiate against the landlord's interest, not yours. Run a competitive bid with at least three qualified contractors for any fit-out above USD 5M.

## Editorial provenance

Reviewed by [**Class A Atlas Editorial Desk**](/about/authors/class-a-atlas-editorial-desk) — House byline · global editorial team. Last updated 2026-04-01. See our [methodology](/about/methodology) and [editorial standards](/about/editorial-standards).

### Primary sources for this page

- [CBRE Marketview reports](https://www.cbre.com/insights) — CBRE
- [JLL Office Insight](https://www.jll.com/en/trends-and-insights) — JLL
- [Cushman & Wakefield Marketbeat](https://www.cushmanwakefield.com/en/insights) — Cushman & Wakefield
- [Savills World Research](https://www.savills.com/research_articles/) — Savills
- [Colliers Global Office Outlook](https://www.colliers.com/en/research) — Colliers

[Full sources index](/about/sources) · [Submit a correction](/about/corrections)